Special Studies for Mike O’Callaghan Federal Medical Center, Las Vegas, Nevada
|
Size |
72,600 square feet renovation
|
| Completion Date | 2015
|
| Responsibilities Naresh S. Mathur, AIA
|
Special studies (see below), Value Engineering, Cost Estimating
|
| Construction Cost | $80 million |
Provided technical studies for infrastructure upgrade associated with hospital and central plant modernizations. Evaluated infrastructure deficiencies, recommended solutions and developed associated costs for up-grades. Conducted on-site evaluation of building, developed Performance Work Statements for Design-Build RFP and prepared cost estimates for the proposed work.
Our services included:
- Investigation of slab-on-grade failure at the existing hospital including on-site field density soil tests to assess structural integrity and recommended solutions in Performance Work Statement
- Investigation of Emergency Power Supply System (EPSS), Transient Voltage System (TVS) and recommendations for upgrade in Performance Work Statement
- Investigation of Fire and Life safety systems for code and life safety compliance and recommendations for repair
- Cost estimating utilizing MCACES – MII (Micro-Computer Aided Cost Estimating System, Second Generation)
- Conducting a Value Engineering workshop
Owner’s contract had an aggressive schedule. Our team proactively responded with innovative approaches, concise narratives and submission of deliverables to the owner ahead of their schedule.